On December 26, 2005, the marketing department of Pu'er Bus Company received a call from the Three Gorges Corporation. On the phone, a business person in charge of the Three Gorges Corporation was responsible for the performance of the PuTang 40-ton wrecker that was just put into use. Give a high rating.

In November 2005, the Three Gorges Corporation asked the car company to build a 40-ton wrecker for them and requested delivery in mid-December. At present, including China United, only three domestic manufacturers have the ability to make 40 tons of wreckers, and because the product safety performance is not guaranteed, it is rare to enter the market.

Three years ago, the winning bidder of the production of wreckers started the development of 40 tons of wreckers. However, for various reasons, there was no product for sale. In May last year, the winning bidder turned the project together. The Pudong Special Vehicle Company, the centralized production unit of the Zhonglian Group wrecker, was given research and rectification.

In the case of tight time and heavy tasks, the car company set up a 40-ton wrecker rectification team headed by the chief engineer Liu Guoliang. On the basis of the development of the winning bidder, after more than a month of intense work, it was finally completed on schedule. The rectification and trial mission was successfully carried out on the 19th.

The 40-ton wrecker developed this time is equipped with advanced configuration. It adopts the original Mercedes-Benz chassis imported from Germany, which greatly improves the reliability of the vehicle. It is equipped with an electronic control system and uses the computer to display the working conditions, so that the operator can rotate the arc. The working condition parameters such as the lifting angle are clear at a glance; in addition to the conventional safety device, a torque limiter is additionally installed. Once the weight of the lifting device exceeds the rated weight, the operating system will be automatically cut off; two winches can be installed. It can expand the function of the wrecker, save the ambulance cost of the vehicle, and make the situation that the wrecker and the crane move at the same time become history; expand the scope of work, the maximum working distance is more than 40 meters, and ambulance for complex terrain Work has increased convenience.

At present, the development of wreckers to large and medium tonnage is a trend. The development of the 40-ton wrecker was successful and went to the market, which seized the market opportunity and greatly improved the Pu's ability to develop and manufacture wreckers.

According to the information from the Three Gorges Corporation, the Pudong 40-ton wrecker has successfully carried out three difficult rescues and is in good working condition. At the same time, they also expressed their intention to continue cooperation with Pudong next year.